Planning for a Bigger Grid

This week's edition follows utilities and governments trying to build ahead of load growth without losing sight of reliability or bills.

Robert Ingram

Robert Ingram

Estimated Reading Time: 7 minutes

The Grid Watch hit 100 subscribers across 2 provinces and I am so happy and grateful for you all!! In celebration, I would like to announce the addition of our new 'Big Read', 'Spotlight' and 'Events' sections, let me know what you think! - Rob

In this week's issue...

🔹 Maritime provinces weigh a regional electricity operator and new undersea cables.

âš¡ B.C. moves its first utility-scale battery project toward procurement.

📊 C.D. Howe tests Saskatchewan's coal-to-SMR bridge against gas-renewable alternatives.

Maritime premiers announce regional electricity co-operation

Maritime premiers announce regional electricity co-operation in Charlottetown. Source: CBC News.

National Headlines

3 Maritime provinces to consider regional electricity operator

CBC News, July 23rd 2026

New Brunswick, Nova Scotia and P.E.I. signed an MOU to create a regional electricity road map by next spring and study an independent Maritime system operator. The deal also includes federal planning support for two new 200-MW undersea cables between New Brunswick and P.E.I., with related transmission and substation work targeted for construction by 2028.

Ottawa proposes major-project review changes affecting transmission decisions

Government of Canada, July 2026

Canada's discussion paper on major-project approvals proposes single project authorities and shorter, clearer timelines. For federally regulated power lines, pipelines and offshore energy projects, the paper says the Canada Energy Regulator would remain the expert decision-maker, with smaller projects receiving reduced decision timelines and larger projects getting earlier public-interest decisions.

The Big Read

The High Cost of Coal-Fired Power as a Bridge to Nuclear

C.D. Howe Institute, July 23rd 2026 | Perspective | Score: 90/100

Brett Dolter argues Saskatchewan's plan to extend coal generation until SMRs arrive would cost ratepayers more than a gas-and-renewables bridge. His modelling estimates a coal-to-SMR path would add 116 to 119 megatonnes of emissions from 2030 to 2050 and cost $696 million to $1.1 billion more per year on average than scenarios pairing new gas capacity with wind and solar. For utilities, the piece is less about one technology preference than about sequencing: dispatchable backup, emissions rules, capital timing and rate impacts all have to be solved together.

Regional Roundup

Manitoba Hydro's energy plan set to be scrutinized

Winnipeg Free Press, July 27th 2026

The Public Utilities Board opened six weeks of hearings into Manitoba Hydro's 10-year integrated resource plan and major new facilities review. The plan includes proposed Brandon natural-gas turbines, Indigenous-owned wind farms and options for meeting demand while the Crown utility manages a projected energy shortfall, aging assets and roughly $25 billion in debt.

B.C. announces first utility-scale battery storage project

CBC News, July 20th 2026

BC Hydro selected a site near Duncan for British Columbia's first utility-scale battery energy storage project. The project is expected to provide at least 100 MW of flexible capacity by 2030, storing power when demand is lower and dispatching during peaks. BC Hydro plans to launch supplier qualification by the end of July.

Champlain Hudson Power Express transmission infrastructure

Champlain Hudson Power Express transmission infrastructure. Source: Montreal Gazette.

New power line between Quebec and New York is down again

Montreal Gazette, July 2026

The Champlain Hudson Power Express, which began commercial service in May, experienced a second outage on the U.S. portion of the line. Hydro-Québec said the outage does not threaten Quebec supply because exports can move through other routes and domestic security remains the utility's first obligation.

Utility Spotlight
BC Hydro
Corporate Profile

Founded: 1961
CEO: Charlotte Mitha
Ownership: B.C. Crown corporation
Revenue: $7.48B (FY2025)
Regulator: BCUC
Workforce: 7,400+ employees

Grid & Operations

Customers: ~5 million people served
Capacity: 13,446.7 MW
Peak Load: 10,476 MW
Gen Mix: Mostly renewable hydro
Grid Lines: 80,873 km
Service Area: 95% of B.C.'s population

Strategic Focus & Partners

BC Hydro is B.C.'s integrated Crown electric utility, balancing large hydro assets, transmission growth, conservation and electrification under its 2024/25 service plan.

Major Projects & Challenges

Battery storage: The Duncan project introduces utility-scale storage into B.C.'s planning toolkit.

Public charging: BC Hydro plans to grow its fast-charging network to 3,500 ports by 2035.

Current challenge: Load growth, weather resilience and electrification are all pushing capital needs higher.

Policy & Pricing

'Eight credible threats' against Hydro employees: CEO

Winnipeg Free Press, July 27th 2026

Manitoba Hydro CEO Allan Danroth told PUB hearings the utility is managing eight credible threats against employees, including five directed at him. The statement came as Hydro defended its integrated resource plan and proposed Brandon combustion turbines, while interveners questioned cost, gas reliance and customer impacts.

Ontario demand data keeps peak-load planning in focus

Independent Electricity System Operator, July 26th 2026

IESO's power-data dashboard listed Ontario's top Industrial Conservation Initiative demand peak at 25,646 MW for July 14, with July 2026 already dominating the province's current base-period peak tracker. For large consumers and distributors, the data reinforces how heat, electrification and conservation programs shape system planning and Global Adjustment exposure.

Adrian Dix headshot
Minister Spotlight
Hon. Adrian Dix
The Vitals

Role: Minister of Energy and Climate Solutions
Province: British Columbia
Age: Not disclosed
Hometown: Vancouver, B.C.
Current Term: 2024 - Present

Mandate & Responsibilities

Dix's portfolio covers provincial electricity policy, BC Hydro oversight, efficiency programs and transportation-electrification files.

The Track Record So Far

Storage: Announced B.C.'s first utility-scale battery storage project near Duncan.

Charging: Backed a $700-million expansion of BC Hydro's public charging network.

Growth planning: Placed both announcements inside BC Hydro's Powering Growth strategy.

On the Radar

"As demand for electricity continues to grow throughout British Columbia, we are making strategic investments."

— Battery storage announcement near Duncan (July 20, 2026)

Innovation & Transition

BC Hydro adds 13-port fast-charge hub in Richmond

BC Hydro, July 2026

BC Hydro opened a new EV fast-charge hub at Kwantlen Polytechnic University's Richmond campus, with room for 13 vehicles. The release says the site supports a broader $700-million plan to more than triple the utility's public charging network to 3,500 ports by 2035.

Ontario utilities launch EV load-management AI project

The Globe and Mail, July 21st 2026

BluWave-ai and four Ontario utilities launched a province-wide EV and distribution-grid load-management project. The initiative involves Oshawa Power, Oakville Hydro, Enova Power and Essex Powerlines, using connected EVs to manage local transformer and substation constraints while supporting IESO grid stability.

Sep
15
Events
Generation Reliability Workshop

Location: Vancouver, BC  •  Cost: Members only

Electricity Canada member workshop focused on generation reliability and utility-sector peer exchange.

Register Here

Worth Noting

P.E.I. premier keeps undersea cable expansion on Ottawa's radar. Read More

CBC News, July 27th 2026

Electricity Canada recognizes utility members for employee-safety performance. Read More

Electricity Canada, July 2026

Hydro-Quebec contract supports planned St. Lawrence hydrokinetic pilot. Read More

Le Devoir, July 2026

Enjoying this brief? Share it with a colleague.

Subscribe to Grid Watch here

Have a news story we should cover, a tip, or thoughts on this edition? Send it over.

Want to reach this audience? Sponsor a future edition.

Grid Watch | By Action Intelligence Group (AIG) | 421 Mulvey Ave, Winnipeg, MB, Canada

 | 

© 2026 Action Intelligence Group. All rights reserved.